CJEU flexibilises treatment of formally non-compliant bids in public procurement (C-336/12)

In its Judgment of 10 October 2013 in case C-336/12 Manova, the Court of Justice of the EU (CJEU) has  followed its own approach in Slovensko and created some room for the flexible interpretation of the rules on formal compliance of bids submitted in public procurement procedures.
 
In Manova, the contracting authority had requested some of the tenderers to provide financial statements that had not been included in their bids after the deadline for their submission had ellapsed. Given that this decision was challenged on the grounds of a potential breach of the principle of equal treatment, the referring court decided to request a preliminary ruling from the CJEU, which was asked "whether the principle of equal treatment is to be interpreted as precluding a contracting authority from asking a candidate, after the deadline for applying to take part in a tendering procedure, to provide documents describing that candidate’s situation – such as a copy of its published balance sheet – which were called for in the contract notice, but were not included with that candidate’s application".
 
In rather clear terms (although some caveats may have been dispensed with, in my opinion), the CJEU ruled that:
the principle of equal treatment must be interpreted as not precluding a contracting authority from asking a candidate, after the deadline for applying to take part in a tendering procedure, to provide documents describing that candidate’s situation – such as a copy of its published balance sheet – which can be objectively shown to pre-date that deadline, so long as it was not expressly laid down in the contract documents that, unless such documents were provided, the application would be rejected. That request must not unduly favour or disadvantage the candidate or candidates to which it is addressed (C-336/12 at para 42).
In my view, the Manova Judgment must be welcome, both for its functional approach and for its alignment with domestic practices in a significant number of EU Member States--as discussed in Sánchez Graells, A, "Rejection of Abnormally Low and Non-Compliant Tenders in EU Public Procurement: A Comparative View on Selected Jurisdictions", in S Treumer and M Comba (eds), Award of Public Contracts under EU Procurement Law, vol. 5 European Procurement Law Series, (Copenhagen, DJØF, 2013) 267-302. This seems a good step in the direction of avoiding that overly strict formal requirements get in the way of actual good public procurement practices.