CJEU backs automatic exclusion of tenderers that had relied on no longer qualified third parties (C-223/16)

nablo-eggs.jpg

In its Judgment of 14 September 2017 in Casertana Construzioni, C-223/16, EU:C:2017:685, the Court of Justice of the European Union (CJEU) has confirmed the legality of the automatic exclusion of an economic operator that had relied on the capacities of an auxiliary undertaking, where the latter lost the required qualifications after the submission of the tender. The CJEU has ruled that the relevant provisions of Directive 2004/18/EC (Arts 47(2) and 48(3)) did not preclude such automatic exclusion, and that they did not require offering the concerned tenderer the possibility to replace the now not-qualifying auxiliary undertaking.

In doing so, the CJEU has followed the Opinion of Advocate General Wahl (criticised here), and created a precedent that is at odds with the new rules in Directive 2014/24/EU (Art 63) and that raises new interpretive difficulties. This post will first rehearse the main reasons why AG Wahl's and now the CJEU's approach is criticisable. It will then look into the interpretive difficulties that can carry through to the interpretation of Article 63 of Directive 2014/24/EU.

Not necessarily a proportionate or pro-competitive approach

In a nutshell, the reasons given by the CJEU to accept the automatic exclusion of a tenderer that relied on the capacities of an auxiliary undertaking that disappear once the offer has been submitted are the same as those of AG Wahl, and are summarised by the CJEU as follows:

as the Advocate General observed ..., the possibility afforded, unpredictably, exclusively to a consortium of undertakings to replace a third-party undertaking which belongs to that consortium and has lost a qualification that is required in order not to be excluded would amount to a substantial change of the tender and the very identity of the consortium. Indeed, such a change of the tender would compel the contracting authority to carry out new checks whilst at the same time granting a competitive advantage to that consortium which might attempt to optimise its tender in order to deal better with its competitors’ tenders in the procurement procedure at issue.

Such a situation would be contrary to the principle of equal treatment which requires that tenderers be afforded equality of opportunity when formulating their bids and which implies that the bids of all tenderers must be subject to the same conditions, and would amount to a distortion of healthy and effective competition between undertakings participating in a public procurement procedure (C-223/16, paras 39-40, emphasis added).

This encapsulates three reasons: (i) discrimination because one consortium is given the opportunity and other tenderers are not, (ii) discrimination because the beneficiary consortium can substantially alter the terms of its tender, and (iii) additional work for the contracting authority. In my opinion, the first reason is spurious because the opportunity to substitute would only arise where a consortium is affected by the loss of qualification of one of its auxiliary undertakings and, barring a case where two or more competing consortia found themselves in that predicament, there is no discrimination for allowing substitutions on a need basis.

The second reason is equally unpersuasive, in particular because it conflates the strict issue of substitution of the member of a consortium with the separate problem of changes to the content of the tender. As I said in relation to AG Wahl's Opinion, provided that the way in which the contracting authority allowed for the substitution between third entities on which capacity the tenderer relied did not confer a competitive advantage to the tenderer, there can be good reasons to allow it. For example, if the application of the qualitative selection criteria did not involve a ranking, but was rather on a pass / no pass basis, and where the terms of the tender were not altered at all because the new entity simply stepped into the shoes of the no longer capable entity, there seems to be limited scope to consider that the tenderer derives a competitive advantage (for more details, see here). Thus, rather than excluding the possibility altogether, the CJEU could have imposed conditions to establish what is an acceptable substitution of auxiliary undertakings and what is not.

Finally, the point on additional checks being required from the contracting authority is relevant. However, rather than considering it a sufficient reason to prevent the substitution, a proportionality assessment would have seemed more appropriate. Given that the exclusion narrows down competition for the contract, the contracting authority should be able to demonstrate that there are sufficient administrative difficulties to justify proceeding this way.

Thus, in outline, I would have preferred that the CJEU departed from AG Wahl's Opinion and declared that the general principles of EU procurement law, and in particular the principle of proportionality coupled with the principle of competition, oppose the automatic exclusion of tenderers that have relied on the capacities of third parties that later lose them, unless the contracting authority can demonstrate that allowing for the substitution of the third party would either infringe the principles of equal treatment, non-discrimination and the obligation of transparency (eg in a situation where the qualitative selection criteria were not assessed on a pass/no pass basis), or would create a disproportionate administrative burden or delay in the conclusion of the procurement procedure. This could create closer functional compatibility in the case law on reliance on third parties and on subcontracting, which I think are currently at risk of imposing functionally incompatible interpretations of the relevant EU public procurement rules.

In my view, my preferred interpretation is encapsulated in Article 63(1) of Directive 2014/24/EU, in particular as read in the light of the principle of competition in Article 18(1) thereof [see A Sanchez-Graells, Public procurement and the EU competition rules, 2nd edn (Hart, 2015) 315-318]. However, the Casertana Judgment may raise some questions around that approach, which requires some closer analysis.

New doubts concerning Article 63(1) of Directive 2014/24/EU

In the Casertana Construzioni Judgment, the CJEU follows its previous approach in Partner Apelski Dariusz (paras 82-94, see here) and the Opinion of AG Wahl and rejects both (i) the application of Article 63(1) of Directive 2014/24/EU to the case ratione temporis (which is uncontroversial, as the tender took place in 2013) and (ii) the possibility of interpreting the rules of Directive 2004/18/EC in light of Article 63(1) of Directive 2014/24/EU. Casertana reiterates the finding in Partner that Article 63(1) of Directive 2014/24/EU introduces 'substantial amendments as regards the right of an economic operator to rely on the capacities of other entities in the context of public contracts' (C-223/16, para 26) and is therefore not suitable as an interpretive tool in relation to Directive 2004/18/EC because the latter is not affected by 'problems of interpretation' (C-223/16, para 28). However, the case is not limited to ignore Article 63(1), but rather seems to consolidate a strict interpretation of this provision. Additionally, given the divergence between Article 63(1) of Directive 2014/24/EU and the Casertana Judgment, the latter creates a potential difficulty concerning the cut-off point at which the possibility to replace non-qualified third parties ends.

Seemingly too restrictive (implicit) interpretation of Article 63(1) of Directive 2014/24/EU

Both the Partner and Casertana cases stress that the new rules foresee that "Article 63(1) of Directive 2014/24 now provides that economic operators may ‘only rely on the capacities of other entities where the latter will perform the works or services for which these capacities are required’ ... and that ‘the contracting authority shall require that the economic operator replaces an entity which does not meet a relevant selection criterion, or in respect of which there are compulsory grounds for exclusion’" (C-223/16, para 25). The second part of this statement has been discussed above (and could have been reconciled with the pre-2014 rules by operation of the principle of proportionality). The first part of the statement is problematic. 

Indeed, this incipient consolidation of the rules in Article 63(1) could trigger difficulties because, according to its literal wording, the restriction of reliance on third parties where they will perform the work or services for which the capacities are required solely concern "criteria relating to the educational and professional qualifications as set out in point (f) of Annex XII Part II [ie the educational and professional qualifications of the service provider or contractor or those of the undertaking’s managerial staff, provided that they are not evaluated as an award criterion], or to the relevant professional experience" -- or, in other words, economic operators are allowed to rely on financial, economic and other types of professional qualifications of third parties even if those parties will not directly carry out the works. This comes to allow for consultancy and technical support contracts to back up the tenders of economic operators that may not have all those resources in-house and is generally pro-competitive. By adopting a blanket approach to the requirement of direct involvement in the execution of the contract beyond the limited remit established in Article 63(1) of Directive 2014/24/EU, a broad reading of the Casertana and Partner cases could deactivate large parts of the flexibility for the formation of consortia that are inherent to the system.

In the specific case of Casertana, all we know is that 

Casertana participated in the call for tenders within the framework of an ad hoc tendering consortium under formation, as lead company, and declared that it relied, as regards the qualifications required by [the applicable Italian rules], on those of two auxiliary undertakings, one being Consorzio Stabile GAP. 

In the course of the procedure and after the end of the stage of admission to the call for tenders, that auxiliary undertaking [is Consorzio Stabile GAP] lost qualification for the required category of services, thus becoming qualified for a lower category of services only (C-223/16, paras 11-12).

Put simply, it is not known why Consorzio Stabile GAP saw its qualification reduced for a lower category of services. If the reasons were not linked to the educational and professional qualifications of its managerial staff or the relevant professional experience of the undertaking, then an acritical application of the decision of the CJEU to the case would imply an unnecessary (and illegal) restriction of the flexibility foreseen in Article 63(1) of Directive 2014/24/EU.

Unresolved timing issues -- when does Article 63(1) of Directive 2014/24/EU stop applying?

In Casertana, the CJEU simply indicated that there is no requirement to give the tenderer an opportunity to substitute auxiliary undertakings that have lost the required qualifications after the tender has been submitted because that would amount to allowing for a substantial change of the tender (see above). It also indicated that tenderers could not claim force majeure (or, more generally, the unpredictability of the loss of qualification by the auxiliary undertaking) to gain such an opportunity to substitute them because, although the procurement rules enable "a tenderer to rely on the capacities of one or more third party entities in addition to its own capacities in order to fulfil the criteria set by a contracting authority, that tenderer remains responsible, in its capacity as the lead undertaking in a consortium of undertakings, for the compliance of those undertakings with the obligations and conditions for participation in the call for tenders laid down by the contracting authority in the documents relating to the procurement procedure at issue" (C-223/16, para 41). A question arises on how to interpret these two issues in situations where Article 63(1) of Directive 2014/24/EU is applicable.

Taking the second aspect first, it seems clear that under Article 63(1) of Directive 2014/24/EU, the responsibility for ensuring compliance with the selection criteria included in the call for tenders is shared between the lead undertaking and the contracting authority. In that regard, it is worth emphasising that the provision foresees that

The contracting authority shall ...verify whether the entities on whose capacity the economic operator intends to rely fulfil the relevant selection criteria and whether there are grounds for exclusion ... The contracting authority shall require that the economic operator replaces an entity which does not meet a relevant selection criterion, or in respect of which there are compulsory grounds for exclusion. The contracting authority may require or may be required by the Member State to require that the economic operator substitutes an entity in respect of which there are non-compulsory grounds for exclusion.

Given this wording, and in case the contracting authority issues a favourable opinion on the qualifications held by a given auxiliary undertaking (or fails to check them, as was the case in Casertana, where the loss of qualification was only raised in the context of a counter-claim against Casertana's challenge to the award of the contract to a different consortium), issues will arise concerning legitimate expectations, in particular concerning the ability to replace no loner qualifying third parties at any point of the procurement process, all the way through to award (including any litigation concerning findings of loss of compliance with selection criteria at tender evaluation stage). However, this would be in stark contrast with the first aspect of the Casertana Judgment, which considers a substitution of auxiliary undertaking an impermissible tender modification. Therefore, the question will arise whether Article 63(1) is applicable throughout the procurement procedure, or only up to the point of submission of tenders.

In my view, the answer to the question cannot be all-or-nothing (as has been the case in AG Wahl's Opinion and in the Judgment), but rather require an analysis of the terms of the substitution (if the new auxiliary undertaking simply assumes all obligations of the previous undertaking in the exact same conditions, where is the advantage?), as well as a proportionality assessment of any new verification work required from the contracting authority as a result of the substitution (in the Casertana case, the issue revolved around qualifications administered by a third party [ie a Certification Body], so it would have seemed rather easy to substitute auxiliary undertakings without requiring much from the contracting authority). Failing that, there is a risk of limiting Article 63(1) to a one-shot remedial opportunity restricted to the contracting authority's first assessment of the tenderer's (and its auxiliary's) compliance with exclusion and qualitative selection rules. Even if this would be an improvement over the 2004 system (in particular as interpreted in Casertana), it would fall short from the flexibility that can be derived from a broader and more dynamic reading of Article 63(1) of Directive 2014/24/EU.