Exclusion grounds are now established in reg.57 of the Public Contracts Regulations 2015 (PCR2015), which follows closely Article 57 of Directive 2014/24. The rules establish three groups of exclusion grounds: mandatory, hybrid and discretionary; as well as some minimum and maximum requirements concerning the timing of the exclusion and its duration. The main novelty concerns the regulation of self-cleaning mechanisms aimed at restoring reliability of economic operators affected by exclusion grounds. 

The following comments are based on my paper "Exclusion, Qualitative Selection and Short-listing", in F Lichère, R Caranta & S Treumer (eds), Modernising Public Procurement. The New Directive, vol. 6 European Procurement Law Series (Copenhagen, DJØF, 2014) 97-129, where further references are provided. All references are to the provisions in Dir 2014/24, but they apply mutatis mutandis to reg.57 PCR2015. I know that the comments are long, but I hope they will be useful. Pedro has complemented them with some views and references, particularly on self-cleaning.

(1) Extension of the grounds for mandatory exclusion of economic operators: an emphasis on the fight against fraud and corruption
Art 57 of Dir 2014/24 alters and extends the grounds for mandatory exclusion currently foreseen in Article 45 of Directive 2004/18. According to Art 57(1) of Dir 2014/24, the current four grounds for mandatory exclusion of economic operators convicted by final judgment are maintained, which include the following offences: i) participation in a criminal organisation, ii) corruption, iii) fraud, and iv) money laundering. The references to the statutory instruments where these offences are regulated have been updated, but the regime remains substantially identical. However, Art 57(1) and 57(2) of
Dir 2014/24 significantly extend the remit of the grounds for mandatory disqualification. 
Reg.57(1)(n) PCR2015 tries to cover this expansion of grounds by including a catch-all final renvoi provision that comprises any offence within the meaning of Art 57(1) of Dir 2014/24 as defined by the law of any jurisdiction outside England and Wales and Northern Ireland; or created, after the day on which these Regulations were made, in the law of England and Wales or Northern Ireland. Hence, the enforcement of this provision will not be without difficulty, given the variety of criminal laws that might need checking, but it seems in line with the requirements of Article IV:4(c) of the revised version of the 2011 WTO Agreement on Government Procurement (GPA), which mandates that contracting authorities conduct ‘covered procurement in a transparent and impartial manner that: (c) prevents corrupt practices’ and which makes explicit reference to the United Nations Convention against Corruption. Therefore, the scope of this ground for mandatory exclusion seems to have been significantly broadened (at least potentially, and depending on the actions of the Member States to adopt aggressive anti-corruption legislation) (see also below). Such broadening can even result in a certain extraterritoriality in the application of this ground for exclusion when national criminal laws concerned with corruption cover instances of bribery of third country officials following the OECD Convention on Combating Bribery. For general discussion, see the contributions to G M Racca and C R Yukins (eds), Integrity and Efficiency in Sustainable Public Contracts (Brussels, Bruylant, 2014).
Some of the novelties in Dir 2014/24 and the PCR2015 are worth highlighting. Firstly, in connection with corruption, the ground is extended beyond the ‘EU definition’ of this offence and will now cover ‘corruption as defined in the national law of the contracting authority or the economic operator’ [art 57(1)(b) dir 2014/24]. According to regs.57(1)(b) to (d) PCR2015, this covers corruption within the meaning of section 1(2) of the Public Bodies Corrupt Practices Act 1889 or section 1 of the Prevention of Corruption Act 1906, the common law offence of bribery, as well as bribery within the meaning of sections 1, 2 or 6 of the Bribery Act 2010, or section 113 of the Representation of the People Act 1983.
Secondly, in relation to terrorism, two new mandatory grounds for exclusion are created for terrorist financing [art 57(1)(e) dir 2014/24] and for terrorist offences or offences linked to terrorist activities [art 57(1)(d) dir 2014/24]. According to regs.57(1)(f) and (g), this covers any offence listed in section 41 of the Counter Terrorism Act 2008, or in Schedule 2 to that Act where the court has determined that there is a terrorist connection; as well as any offence under sections 44 to 46 of the Serious Crime Act 2007 which relates to an offence coverered by the Counter Terrorism Act 2008.
Thirdly, a new ground for mandatory exclusion is created to tackle child labour and other forms of trafficking in human beings, as defined in the corresponding EU instruments [art 57(1)(f) dir 2014/24]. Regs.57(1) (j) to (m) PCR2015 extend that to any offence under section 4 of the Asylum and Immigration (Treatment of Claimants, etc.) Act 2004, under section 59A of the Sexual Offences Act 2003, section 71 of the Coroners and Justice Act 2009, or  any offence in connection with the proceeds of drug trafficking within the meaning of section 49, 50 or 51 of the Drug Trafficking Act 1994.
Fourthly, lack of payment of taxes or social security contributions becomes a ground for mandatory disqualification where this has been established by a judicial or administrative decision having final and binding effect in accordance with the legal provisions of the country in which it is established or with those of any of the jurisdictions of the United Kingdom [art 57(2) dir 2014/24 and reg.57(3) PCR2015]. This makes mandatory the grounds for discretionary exclusion previously foreseen in Arts 45(2)(e) and 45(2)(f) of Dir 2004/18 where there is a final and binding jurisdictional or administrative decision—and, otherwise, it will remain a discretionary ground for exclusion under Art 57(2)II of Dir 2014/24 / reg.57(4) PCR2015 (see below). 
Lastly, Art 57(1) in fine of Dir 2014/24 [reg.57(2) PCR2015] clarifies the provisions in Art 45(1) in fine of Dir 2004/18 and extends the obligation to exclude the economic operator on the basis of any of the prior grounds for exclusion ‘where the person convicted by final judgment is a member of the administrative, management or supervisory body of that economic operator or has powers of representation, decision or control therein’. The only exception to this rule concerns the lack of payment of taxes and social security contributions, but this seems open to contention. In my opinion, at least where lack of payment is related to the activities of the economic operator, the rule should apply despite the legal person not being the one directly convicted or the direct addressee of the jurisdictional or administrative decision confirming the breach of tax or social security rules. 
 
It is also worth stressing that, similar to what was already provided for in Art 45(1)III of Dir 2004/18, Art 57(3) of Dir 2014/24 [reg.57(6) PCR2015] foresees that ‘Member States may provide for a derogation from the mandatory exclusionon an exceptional basis, for overriding reasons relating to the public interest such as public health or protection of the environment’. In this regard, I would submit that the interpretation of the concept of ‘general interest’ developed by the CJEU in the area of free movement (of goods, in relation to art 36 TFEU and the so called Cassis rule of reason) may be of relevance for the interpretation and construction of such potential derogations. 
Moreover, in the case of the lack of payment of taxes and social security contributions, Art 57(3) in fine of Dir 2014/24 [reg.57(7) PCR2015] authorises Member States to create an (additional) derogation ‘where an exclusion would be clearly disproportionate, in particular where only minor amounts of taxes or social security contributions are unpaid or where the economic operator was informed of the exact amount due following its breach of its obligations relating to the payment of taxes or social security contributions at such time that it did not have the possibility of taking measures [addressed at sorting out the situation …] before expiration of the deadline for requesting participation or, in open procedures, the deadline for submitting its tender’. 
In order to ensure consistency of such a de minimis exception to the mandatory rule established in Art 57(2) of Dir 2014/24, a common definition of what constitutes ‘minor amounts’ seems necessary. Otherwise, this is an issue likely to end up being referred to the CJEU for a preliminary interpretation, which answer may be almost impossible for the Court to provide, unless it is clearly willing to create a judicial de minimis threshold for this ground of exclusion [which it is extremely unlikely, particularly in view of the formalistic approach followed in the recent decision in Consorzio Stabile Libor Lavori Pubblici, C-358/12, EU:C:2014:2063] .

(2) Extension of the discretionary grounds for exclusion of economic operators
Following the distinction in Art 45(2) of Dir 2004/18, which established additional exclusion grounds that contracting authorities can decide to apply at their discretion, Arts 57(2)II and 57(4) of Dir 2014/24 extend the current list of discretionary grounds for the exclusion of economic operators that contracting authorities may decide to use (or may be required by their Member State to use) to exclude any economic operator from participation in a procurement procedure. 
With some drafting modifications, but with fundamentally the same content, the list provided in Arts 57(2)II and 57(4) covers the current grounds of exclusion on the basis of: i) bankruptcy, judicial administration or assimilated situations, including being part of ongoing proceedings, ii) demonstrated grave professional misconduct, which renders its integrity questionable, iii) lack of payment of taxes or social security contributions not established by a jurisdictional or administrative decision having final and binding effect (otherwise, the exclusion ground becomes mandatory, above), and iv) serious misrepresentation in supplying the information required for the verification of the absence of grounds for exclusion or the fulfillment of the selection criteria, or withholding of such information. Furthermore, and similarly to what happened with mandatory exclusion grounds, Art 57(4) of Dir 2014/24 extends and broadens the list of situations in which an economic operator can (or must) be excluded. This is covered by regs.57(4) and (8) PCR2015. Some provisions deserve additional comments.
Firstly, given the creation of new rules on the European Single Procurement Document (ie the submission of self-declarations) rather than the supply of full evidence supporting the inexistence of grounds for exclusion and compliance with qualitative selection criteria (art 59 dir 2014/24), the ground concerned with misrepresentation and withholding of information is extended to cover situations where the economic operator is ‘not able to submit the supporting documents required pursuant to Article 59’ [art 57(4)(h) dir 2014/24]. This establishes a iuris et de iure presumption that the economic operator that cannot supply the required supporting documentation has gravely misrepresented its suitability and qualification to be awarded the contract and seems a natural extension of this grounds for exclusion—which, in my opinion, should however be a mandatory ground for exclusion. 
Secondly, contracting authorities can exclude economic operators where they can demonstrate by any appropriate means violations of applicable obligations established by Union law or national law compatible with it in the field of social and labour law or environmental law or of the international social and environmental law provisions listed in Annex X [arts 18(2) and 57(4)(a) dir 2014/24]. Other than the considerations related to the use of public procurement as a lever to reinforce compliance with such ‘secondary policies’, this new ground for exclusion raises the issue of the standard of diligence that the contracting authority must discharge in order not to be negligently unaware of the existence of such violations. Given that there are different standards for different exclusion grounds, these are issues that are prone to litigation and that will likely require interpretation by the CJEU. In my view, any means of proof should suffice to proceed to such exclusion, but the violation should be of a sufficient entity as to justify the exclusion under a proportionality test (similarly to what the new Directive proposes in terms of lack of payment of taxes or social security contributions, or ‘grave’ professional misconduct), since exclusion for any minor infringement of social, labour or environmental requirements may be disproportionate and, ultimately, not in the public interest if it affects the level and intensity of competition for the contracts. 

Thirdly, the Directive creates a new (limited) ground for the exclusion of infringers of competition law. Indeed, contracting authorities can now exclude economic operators where they have ‘sufficiently plausible indications to conclude that the economic operator has entered into agreements with other economic operators aimed at distorting competition’ [art 57(4)(d)]. This should be read in connection with the OECD’s July 2012 Recommendation on Fighting Bid Rigging in Public Procurement and with the many actions undertaken by national competition authorities of some of the Member States to better liaise with contracting authorities and entities, and to advocate for competition law compliance in the public procurement setting. 
In my opinion, this new ground for exclusion is excessively limited and, given the gravity of bid rigging, it should be a ground for the mandatory exclusion of the offenders [see A Sanchez Graells, ‘Prevention and Deterrence of Bid Rigging: A Look from the New EU Directive on Public Procurement’, in G M Racca and C R Yukins (eds), Integrity and Efficiency in Sustainable Public Contracts (Brussels, Bruylant, 2014) 137-157]. As a matter of diligence (and subject to applicable domestic rules), in these cases, the contracting authority seems likely to be under a duty to report this behaviour to the national competition authority and to cooperate as much as necessary with the ensuing competition law investigation.

Fourthly, the Directive creates yet another ground for exclusion based on poor past performance by the economic operator. Under this new ground, contracting authorities can exclude economic operators that have ‘shown significant or persistent deficiencies in the performance of a substantive requirement under a prior public contract, a prior contract with a contracting entity or a prior concession contract which led to early termination of that prior contract, damages or other comparable sanctions’ [art 57(4)(g)]. The introduction of past performance as an exclusion ground responds to the requests made for a long time by practitioners and brings the EU system closer to that of the US. Remarkably, this provision may overturn the practice and case law that prevented contracting authorities to take past performance into consideration. In my opinion, even if good past performance should not be taken into consideration either for selection or award purposes (because of the effect it has in entrenching the incumbents), it seems sensible to introduce its use for ‘negative’ purposes in order to allow contracting authorities to (self)protect their interests by not engaging contractors prone not to deliver as expected. This seems particularly proportionate in view of the rules on ‘self-cleaning’ that allow contractors to compensate such poor past performance by showing that they have implemented changes to avoid them recurring.

Interestingly, a (soft) corruption-related new ground for exclusion is also created. Further to the ground for mandatory exclusion of economic operators engaged in (hard) corruption (above), contracting authorities can exclude economic operators where they have ‘undertaken to unduly influence the decision-making process of the contracting authority, to obtain confidential information that may confer upon it undue advantages in the procurement procedure or to negligently provide misleading information that may have a material influence on decisions concerning exclusion, selection or award’ [art 57(4)(i) Dir 2014/24]. To be sure, some or all of these activities may be caught by the definition of corruption under domestic laws and, consequently, could substantively overlap with the mandatory ground for exclusion in Art 57(1)(b) of Dir 2014/24 (above). However, the mandatory ground for exclusion is only triggered if the economic operator has already been convicted by final judgment. Consequently, the virtuality of Art 57(4)(i) of Dir 2014/24 resides in allowing the contracting authority to immediately exclude any economic operator engaged in (quasi)corruption or that has otherwise tried to tamper with the integrity of the tender procedure. As a matter of diligence (and subject to applicable domestic rules), in these cases, the contracting authority seems likely to be under a duty to report this behaviour to the competent authorities or courts and to push for criminal prosecution.

Finally, and strengthening the general remarks contained in the recitals of previous generations of procurement directives, the new Directive has also created two complementary grounds for the exclusion of tenderers in cases of conflict of interest, either generally [arts 24 and 57(4)(e)], or as a result of the prior involvement of candidates or tenderers in the preparation of the procedure [arts 41 and 57(4)(f)]. Indeed, the contracting authority can exclude economic operators ‘where a conflict of interest within the meaning of Article 24 cannot be effectively remedied by other less intrusive measures’ , or ‘where a distortion of competition from the prior involvement of the economic operators in the preparation of the procurement procedure, as referred to in Article 41, cannot be remedied by other, less intrusive measures’. These provisions should allow contracting authorities to ensure the integrity of the procurement process, despite the fact that the conflict of interest will also affect themselves (or members of their staff) and, consequently, these may end up being provisions which disappointed tenderers use in order to challenge their lack of application, rather than provisions directly and positively applied by the contracting authorities themselves—depending, of course, on the institutional robustness of the specific contracting authority concerned (and the litigation environment in any given Member State).

 
(3) Exclusion possible at any point of the tender procedure
Art 57(5) of Dir 2014/24 [regs. 57(9) and (10) PCR2015] introduces a much needed clarification on the possibility or duty for contracting authorities to exclude economic operators at any moment during the procedure. This clarifies that exclusion grounds (both those that are mandatory as a matter of EU law, and those that Member States make mandatory in their jurisdictions) should be considered unwaivable [ie mandatory because they represent the ‘public interest’, unless some of them are configured in a discretionary manner by domestic law, as allowed for by art 57(4) dir 2014/24] and that contracting authorities should be aware of them and check for compliance throughout the tender procedure. Equally, contracting authorities are now given express legal support for the exclusion of tenderers at late stages of the tender procedure, therefore nullifying any claims based on the potential (legitimate?) expectations derived from not having been excluded at the beginning of the procedure. According to Article 57(5) of Dir 2014/24, it is now clear that a contracting authority would not be going against its own prior acts and thus not be estopped from excluding tenderers previously admitted to (or not excluded from) the tender procedure.

More specifically, Art 57(5) of Dir 2014/24 establishes that contracting authorities ‘shall at any time during the procedure exclude an economic operator where it turns out that the economic operator is, in view of acts committed or omitted either before or during the procedure,’ convicted by final judgment of one of the qualified crimes of Art 57(1), or where the contracting authority is aware that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions and where this has been established by a judicial or administrative decision having final and binding effect [Art 57(2) dir 2014/24; reg.57(9) PCR2015]. Moreover, ‘contracting authorities may exclude or may be required by Member States to exclude an economic operator where it turns out that the economic operator is, in view of acts committed or omitted either before or during the procedure, in one of the situations referred to in paragraph 4’ [see also reg.57(10) PCR2015]. This new provision is due to generate significant legal effects and may be open to litigation to test its boundaries against the general principles of equal treatment, protection of legitimate expectations and legal certainty—which can raise ‘constitutional’ law issues in some of the domestic jurisdictions.

 
(4) Harmonisation of minimum rules on maximum exclusion periods Following the position in Arts 45(1) and 45(2) of Dir 2004/18, Art 57(7) of Dir 2014/24 requires that Member States specify the implementing conditions for the exclusion of economic operators by law, regulation or administrative provision and always having regard for EU law. However, it establishes new minimum rules concerning maximum exclusion periods. Indeed, Member States shall ‘determine the maximum period of exclusion if no [self-cleaning] measuresare taken by the economic operator to demonstrate its reliability. Where the period of exclusion has not been set by final judgment, that period shall not exceed five years from the date of the conviction by final judgment in the cases referred to in paragraph 1 and three years from the date of the relevant event in the cases referred to in paragraph 4’ of that same Art 57 of Dir 2014/24.
This has been transposed in regs.57(11) and (12) PCR2015, whereby in the cases referred to in paragraphs (1) to (3), the period during which the economic operator shall (subject to paragraphs (6), (7) and (14)) be excluded is 5 years from the date of the conviction; whereas in the cases referred to in paragraphs (4) and (8), the period during which the economic operator may (subject to paragraph (14)) be excluded is 3 years from the date of the relevant event.  
Under the EU regime, in the specific case of (mandatory or discretionary) exclusion due to lack of payment of taxes or social security contributions, the exclusion seems to be subject to an indefinite period that will only finish once the economic operator settles the outstanding debt or enters into arrangements to do so. This derives from Art 57(2) in fine Dir 2014/24 which determines that these grounds for exclusion ‘shall no longer apply when the economic operator has fulfilled its obligations by paying or entering into a binding arrangement with a view to paying the taxes or social security contributions due, including, where applicable, any interest accrued or fines’ [this is also established in reg.57(5) PCR2015]. Reg.57(11) PCR2015 has opted to apply the maximum of 5 years of exclusion to economic operators in breach of their obligations to pay taxes or social security contributions as established by a judicial or administrative decision having final and binding effect [reg.57(3)]. In my view, this can be a deviation from the standard interpretation of Art 57 Dir 2014/24. However, given that it sets a limit to a situation that would otherwise be potentially indefinite, I find it hard that this will trigger litigation or, indeed, a finding of infringement against the UK due to improper transposition.

More generally and in my opinion, such different treatment for specific exclusion grounds under EU law (ie the possibility to indefinitely exclude operators in breach of tax or social security obligations) seems unwarranted and other exclusion grounds that indicate the existence of similarly ongoing infringements (such as those concerned with infringements of social, labour and environmental law, or those concerning bankruptcy and administration) should also be subjected to indefinite exclusion until the economic operator complies with the relevant legislation. This result may be achieved anyway depending on the domestic rules applicable to continued infringements, but some further clarification and harmonisation could be desirable in order to keep the level playing field. Moreover, rules on the recognition of domestic exclusion decisions in the rest of the Member States could also be necessary, although this can be indirectly achieved by the European Single Procurement Document. 

(5) Self-cleaning and corporate compliance programs
As a novelty, and in order to allow ‘for the possibility that economic operators can adopt compliance measures aimed at remedying the consequences of any criminal offences or misconduct and at effectively preventing further occurrences of the misbehaviour’ [rec (102) dir 2014/24], Art 57(6) of Dir 2014/24 [regs.57(13) to (17) PCR2015] establishes rules on self-cleaning and promotes the adoption of corporate compliance programs. Under the rules of Art 57(6) Dir 2014/24, any economic operator that should be excluded under any of the grounds in 57(1) or 57(4) can provide evidence to the effect that measures it has taken are sufficient to demonstrate its reliability despite the existence of a relevant ground for exclusion and, if such evidence is considered as sufficient by the contracting authority, the economic operator concerned shall not be excluded.

The Directive includes a list of compensatory measures that, as a minimum, shall include proof that the economic operator ‘has paid or undertaken to pay compensation in respect of any damage caused by the criminal offence or misconduct, clarified the facts and circumstances in a comprehensive manner by actively collaborating with the investigating authorities and taken concrete technical, organisational and personnel measures that are appropriate to prevent further criminal offences or misconduct’ [reg.57(15) PCR2015]. Furthermore, the discretion retained by the contracting authority to assess the sufficiency of the self-cleaning measures adopted by the economic operator is modulated by the requirement that they ‘shall be evaluated taking into account the gravity and particular circumstances of the criminal offence or misconduct
[reg.57(16) PCR2015]. As a specific requirement of the duty of good administration and the obligation to provide reasons for any decision adopted in a procurement procedure, ‘[w]here the measures are considered to be insufficient, the economic operator shall receive a statement of the reasons for that decision[see reg.57(17) PCR2015]—which, in my opinion, shall be amenable to judicial review under the applicable rules of each Member State.

Oddly, the Directive restricts the possibility of implementing self-cleaning measures for economic operators that have ‘been excluded by final judgment from participating in procurement procedures [which] shall not be entitled to make use of [this] possibilityduring the period of exclusion resulting from that judgment in the Member States where the judgment is effective’. This shows a lack of trust in self-cleaning measures and imposes exclusion as an irreversible sanction in the Member State adopting that decision (but, oddly, not in other Member States), which can sometimes disproportionately reduce competition (as well as creating a dual standard applicable in ‘domestic’ and ‘cross-border’ participation in procurement by that operator). Therefore, in my opinion, self-cleaning should also be available in these cases, which may justify a particularly tough approach to the evaluation of the sufficiency of the measures implemented by the economic operator. At least, an escape clause should exist in these cases to waive, substitute or defer the exclusion on grounds of public interest if having the economic operator excluded actually harms the interests of the contracting authority (which may be the case in highly concentrated or specialised markets)
.

However, even if the exclusion in Art 57(6) in fine of Dir 2014/24 is criticisable, it clearly imposes that '[a]n economic operator which has been excluded by final judgment from participating in procurement or concession award procedures shall not be entitled to make use of the possibility provided for under this paragraph during the period of exclusion resulting from that judgment in the Member States where the judgment is effective'. This provision certainly has direct effect. Consequently, contracting authorities must apply it, regardless of the fact that reg.57 PCR2015 does not include such a rule. Otherwise, in my view, can lead to an investigation by the European Commission for improper transposition of the rules in Art 57 Dir 2014/24 against the UK.